Transpower secures cable supply for Cook Strait electricity link upgrade
The contract confirmation is a major step forward in Transpower’s work to renew the critical High Voltage Direct Current (HVDC) link that connects the North and South Islands’ electricity systems. The link ensures energy security, resilience and the ability to deliver lowest cost electricity to consumers. Key parts of the link, including the undersea cables, are due for renewal in the early 2030s.
Transpower Chief Executive James Kilty said the agreement with Prysmian today is an important milestone and means detailed design can begin immediately.
“The undersea cables required for this project are highly specialised, in high demand globally, and have long lead times to manufacture and install, which is why securing the supply of new cables and specialist installation resources is critical.”
The four new 40 km cables will be delivered to New Zealand and installed in 2031 by a state-of-the-art cable-laying vessel, following onshore works to upgrade the cable termination stations they will connect to.
Mr Kilty said the cables will be designed to meet the specific requirements of New Zealand’s electricity system and installation will be carefully planned to manage the challenging conditions in Cook Strait.
“The electricity flow across the Cook Strait cables can change direction multiple times a day depending on weather, lake levels, generation availability and electricity use. This gives our electricity system resilience and flexibility, but also means we need a particular type of cable that only a small number of suppliers in the world can produce.”
Prysmian is a global leader in the cable industry and designs, manufactures and installs undersea electricity transmission systems. It is headquartered in Milan, Italy, with operations worldwide.
“Prysmian brings significant expertise to this work. We are pleased to be working with them to deliver this important project.”
Today’s confirmation follows the Commerce Commission’s final decision earlier this month to approve Stage One of the HVDC investment programme.
Transpower will now seek environmental approvals for the physical works, including the new cable termination stations and earthworks for cable installation. Subject to approval, work on-site is expected to begin in the summer of 2027/28.