Australia’s energy transition should reward flexibility, not just generation

Most of the debate about Australia’s electricity transition is about what to build: more wind and solar, more transmission, more storage. All of it is needed, but a grid that runs largely on weather-dependent generation also needs something less visible: the ability to adjust at short notice when electricity is scarce or abundant.
Image: Ausgrid

Flexibility means temporarily reducing or shifting electricity use, or dispatching stored or generated energy, when the system needs it.

A manufacturer might slow part of a process without impacting production, a water plant might shift a pumping schedule while still meeting reservoir targets. A site with a battery might draw on it instead of the grid. Large electricity users, in other words, can help stabilise the grid rather than simply adding to demand.

The Australian Energy Market Operator’s (AEMO) 2026 Integrated System Plan shows why this matters. Under its optimal development path, most of the remaining coal fleet would withdraw by 2038. By 2050 the plan has nearly 50 GW of dispatchable storage and hydro, including existing hydro, and 17 GW of flexible gas. It also describes demand-side flexibility as a valuable way to support reliability.

This model doesn’t replace new generation, transmission or storage. Flexible demand is a complement: capacity that already sits inside connected businesses and can respond quickly without necessarily building anything new.

There are several ways flexibility can be paid for, and they are not interchangeable. The Wholesale Demand Response Mechanism lets large electricity users, through a registered provider, be paid for reducing consumption against a baseline.

Frequency control ancillary services (FCAS) are 10 separate markets that pay enabled providers to help hold system frequency steady, with the fastest responding within a second. Emergency reserves, contracted by AEMO under the Reliability and Emergency Reserve Trader, are a backstop, used when a shortfall is forecast and the market has not resolved it.

At state level, South Australia’s Firm Energy Reliability Mechanism has begun contracting long-duration firm capacity under its own criteria.

Each of these mechanisms has distinct eligibility and operating requirements, so a site that suits one may not qualify for another. Even a site that is technically able to respond may not be eligible under the rules, or may be eligible but have no commercial route to take part.

For an eligible business, participation can add a revenue stream from assets it already owns. But not every load can be interrupted, and some processes cannot be paused without consequences for safety, product quality or output.

Those limits have to come first. Technology’s role is to make participation practical within them: monitoring the site, responding to dispatch, demonstrating compliance and reconciling settlement.

The gap between what a site can technically do and what the rules allow is where useful flexibility gets lost. Complex industrial sites are a clear example.

Under the National Electricity Rules, only sites with a single connection point can take part in the Wholesale Demand Response Mechanism. The restriction exists for a reason: a site could cut demand at one connection point while raising it at another, showing a reduction that never happened. However, it also excludes multi-connection sites whether or not that risk could be measured and managed.

Regulators are testing an alternative. In June, the Australian Energy Regulator granted trial waivers of up to five years to two demand response providers, VIOTAS Australia (now PowerSync) and one other, each allowing up to 10 multi-connection sites into the mechanism, with response measured across every connection point and regular public reporting.

The trials are meant to inform the Australian Energy Market Commission, which recommended last year that a rule change request to widen eligibility be assessed.

Wider participation will not fix reliability or lower bills on its own, and it should not be sold that way. What it can do is give the market operator more options to balance the system, and give businesses a way to diversify revenue from assets they have already paid for.

Three principles would help energy market bodies and policymakers get this right. Rules should be proportionate: where a risk can be measured and managed, manage it rather than exclude the site. Performance should be measurable: flexibility should be paid for what it verifiably delivers. And market access should be fair: eligible flexible capacity should be able to compete across wholesale demand response, frequency control and emerging state capacity schemes, with clear pathways for complex sites.

Businesses have a part to play too. The first step is to find out whether existing loads, batteries and on-site assets can safely take part.

While Australia keeps building new supply, it should also reward the capacity it already has for responding when it counts.

Author: David Naismith, founder and Chief Executive Officer, PowerSync Technologies

The views and opinions expressed in this article are the author’s own, and do not necessarily reflect those held by pv magazine.