EnergyCo taps Transgrid to advance Hunter Transmission Project
The New South Wales (NSW) government has awarded Transgrid the contract to build, operate and maintain the Hunter Transmission Project (HTP), a 110-kilometre transmission line designed to bridge a crucial network gap as the state’s ageing coal-fired power stations progressively retire.
The project involves building a new above-ground 500 kV transmission line between Bayswater in the Upper Hunter region and Olney in the Lower Hunter to connect the state’s existing 500 kV transmission lines already operated by Transgrid. It will also include the construction of new switching stations at Bayswater South and Onley State Forest, and upgrades of the existing Bayswater and Eraring substations.

NSW government energy agency EnergyCo said the new infrastructure will form a critical part of the state’s electricity grid, delivering a connection between the New England and Central-West Orana renewable energy zones (REZs) and homes and businesses in the Hunter, Sydney and Illawarra regions.
EnergyCo Chief Executive Officer Hannah McCaughey said the project will enable access to cheaper renewable energy for millions of consumers across the state as coal generation retires. The new infrastructure is expected to unlock up to 5 GW of additional electricity transfer capacity.
“This is a critical piece of infrastructure that will increase the capacity of the electricity network and help unlock new renewable generation and storage,” McCaughey said. “By creating a new 500 kV transmission line and connecting it to existing infrastructure, the HTP will form the backbone of NSW’s future electricity grid.”
EnergyCo, which has led planning and procurement for the Hunter Transmission Project, said the appointment of Transgrid as network operator marks a major milestone for the project and moves it a step closer to construction.
Transgrid will now manage delivery of the project before operating and maintaining the new infrastructure over the long term.
EnergyCo, which will continue its planning and oversight role as infrastructure planner, said design and construction contracts have also been awarded to Downer for transmission lines and UGL for substations, ensuring the project is well positioned to move quickly into the next phase of delivery.
Transgrid Chief Executive Brett Redman said the project team will now focus on detailed design, engineering and management plans before construction begins next year in line with the conditions of approval.
“Our focus now is on delivering this essential transmission infrastructure safely and efficiently for the NSW government as the state transitions to a more reliable, secure and affordable energy future,” he said.
Construction is scheduled to commence in 2027, with the project expected to be fully operational by late 2029.
The project is expected to create 900 jobs during construction and also deliver a wide range of social and economic benefits to the broader Hunter region including supply contracts for local businesses.
EnergyCo said about 90% of the project’s corridor follows mining, energy, and government-owned land, minimising impacts on people, properties, and the environment.