Sydney-headquartered renewable energy company Squadron Energy has lodged a scoping report for its proposed $1.4 billion (USD 980 million) 8 GWh battery energy storage system (BESS) in New South Wales (NSW).
To be located approximately 25 kilometres north of Lithgow, or 170 kilometres northwest of Sydney, the designated State Significant 1 GW / 8,000 MWh Cullen Bullen Battery, has a nominal duration of 8 hours.
A new substation would be constructed to facilitate a connection to NSW high voltage electricity transmission manager Transgrid’s existing onsite overhead 500 kV transmission network.
In early stages of development, Squadron is seeking feedback from the local community to inform the total 660-hectare project’s design and build.
Squadron Energy Project Developer Sean Cross said engaging with the community early and delivering lasting local benefits are priorities for Squadron.
“Squadron is committed to delivering real benefits for local families and businesses through investment in infrastructure, funding for community programs and the creation of local jobs and training opportunities,” Cross said.
“We’re already investing in the local community through our sponsorship program, with funding available to support organisations delivering education and training, community development, health and wellbeing, and environmental initiatives.”
A NSW Department of Planning Secretary’s environmental assessment requirements (SEARs) is expected to be issued in December 2026 and detailed design and construction by 2029, pending necessary approvals, with construction likely in 2030.
The project would be situated 1.1 kilometres northwest of Alinta Energy’s proposed 500 MW wind farm and 200 MW / 800 MWh BESS, 7.8 kilometres southwest from Someva Renewables and Mainstream Renewable Power’s proposed 500 MW wind farm, and 8.1 kilometres southeast from EnergyAustralia’s approved 500 MW / 2 GWh BESS.
Within a 25 kilometre radius of the Cullen Bullen Battery would be the approved 500 MW / 1 GWh Neoen Great Western BESS and the 600 MW Shell Energy Wallerawang BESS, and the proposed 700 MW / 2.8 GWh Centennial Coal Ivanhoe BESS, plus other clean energy projects.