Skip to content

Pumped Hydro

Marinus Link gets go-ahead to dive straight into stage 1 construction phase

Marinus Link, the 750 MW capacity high voltage direct current electricity interconnector proposed to strengthen the Tasmania and Victoria connection on the National Electricity Market, has reached Stage 1 financial investment decision.

Banpu buys into EnergyAustralia battery project

Thai energy company Banpu has snapped up a 50% stake in the 350 MW / 1,400 MWh Wooreen battery energy storage system being built in Victoria’s Latrobe Valley as the Bangkok-based coal producer ramps up investments in renewable energy.

OX2 Muswellbrook solar and battery project approved

The New South Wales Independent Planning Commission has provided the tick of approval for a 135 MW solar farm and a 135 MW / 270 MWh battery project being developed at the site of a former coal mine in the Hunter Valley.

Genex reaches construction milestone on 2 GWh pumped hydro project

Construction of the 2 GWh Kidston pumped storage hydro project being developed in northern Queensland has reached a key milestone with the successful installation of the initial spiral case in the underground powerhouse.

1

NSW targets 1 GW of energy storage with latest tender

New South Wales has launched a new tender seeking 1 GW of long-duration energy storage projects that are each able to continuously dispatch power for at least eight hours at their registered capacity.

2

AGL adds 1.4 GW of pumped hydro projects to pipeline

Australian energy giant AGL has added two pumped hydro projects with a combined capacity of almost 1.4 GW, each with 10 hours of energy storage, to its development pipeline as it works to transition its energy portfolio from coal-fired power generation to backed-up renewables.

Queensland backs 20 GWh pumped hydro project

The Queensland government is set to invest $50 million into a pumped hydro project with an energy storage capacity of up to 20 GWh as it works to develop a new five-year Energy Roadmap that is to be delivered by the end of 2025.

1

Government accelerates approval process for 25 GW of priority renewables projects

More than 16 GW of solar and wind generation and approximately 6 GW of energy storage projects could benefit from an accelerated environmental approvals process as the Australian government works to deliver critical infrastructure needed to achieve its clean energy targets, including 82% renewable electricity by 2030.

Feedback sought on hybrid projects in next CIS tender for Western Australia

On the cusp of Capacity Investment Scheme Tender 2 – WEM Dispatchable successful proponent announcements, the federal government now calls for feedback on how to approach hybrid projects in the pending 2025 WEM Tender for Western Australia, opening mid-2025.

1

Pumped hydro energy storage potential equates to 2 trillion EV batteries: study

A new paper co-authored by Australian National University Professor Andrew Blakers discusses the potential for long-duration pumped hydro energy stations built on non-river locations, which, with batteries, can solve world’s energy storage needs.

3

This website uses cookies to anonymously count visitor numbers. To find out more, please see our Data Protection Policy.

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close