Quinbrook plans to deploy an initial 3 GW / 24 GWh of EnerQB lithium-ion battery energy storage systems developed in a technical collaboration with Chinese battery giant CATL to support major new industry hubs in Queensland, New South Wales (NSW) and the Northern Territory.
Quinbrook said the newly developed EnerQB battery energy storage systems will be teamed with large-scale solar and wind projects to serve both existing partners and new commercial and industrial customers at sites across the country including in Brisbane, Gladstone, and Townsville.
The company said the longer-duration storage solution, when paired with solar PV is capable of delivering one of the most competitively priced power options available today and will help to support-value adding industries in Australia.
David Scaysbrook, co-founder and Managing Partner of Quinbrook, said the EnerQB has been specifically designed to cost effectively time shift more stored solar power than ever before, providing industrial customers with the ability to power a two eight-hour shift manufacturing operation entirely from solar.
“It is a game changer in terms of what it does to the cost of electricity,” Scaysbrook said. “When you put it with solar in places like Queensland that has very high levels of irradiation, it allows us to capture more solar, more hours of the day. We can cost-effectively shift that solar energy. This will be materially more cost competitive than existing batteries.”
“This isn’t the holy grail but it’s getting us closer to 24/7 renewable power.”
Described by Quinbrook as the “world’s first” genuine eight-hour duration lithium-ion battery, the EnerQB comes after two years of design and development alongside battery industry heavyweight CATL.
Quinbrook APAC Managing Director and regional leader Brian Restall said the energy storage solution is much more energy dense than existing technologies, adding that the advance is the result of design enhancements rather than a shift in CATL’s cell technology.
“It is an evolution more in the design of the container,” he said. “It is not to do with the chemistry of the cells, it’s how we do the configuration in the containers to keep the temperature down so it’s got much lower parasitic load.”
Restall acknowledged that there are batteries that run as eight-hour batteries in Australia but stressed there are “no genuine eight-hour batteries” in the country.
“There are other marketing announcements which talk about an eight-hour battery and the configuration but the technology that they are using is a two-hour or four-hour battery designed and run at half speed,” he said. “It’s not a specific design for an eight-hour battery. They are almost 80% less energy dense than the new design and they have 4-5% higher parasitic load than the new design.”
Quinbrook said the EnerQB is an evolution of the solar and battery storage projects it has built in the United States and United Kingdom which use a four-hour duration battery storage solution for the time shifting of solar power to deliver cost competitive renewable power.
“This battery is not a battery that you quickly cycle and arbitrage and play the market,” Restall said. “That’s not what this does. It does one thing every day, same thing every day – full charge and full discharge when the sun goes down.”
Quinbrook said the initial 3 GW of EnerQB projects is already largely committed, with the first of the batteries is be installed at the company’s Supernode battery and data centre project in Brisbane which has now been expanded to include a fourth stage.
Construction has already commenced on the first of the Supernode stages that will deliver a combined nameplate capacity of 760 MW / 3,096 MWh. The fourth stage will add an additional 250 MW / 2,000 MWh capacity and is expected to be delivered before the end of 2026.
“We’re expanding Supernode from three stages to four stages,” Scaysbrook said. “We’ve already got the land, already got the permits and got the interconnection application underway.”
“Our Gladstone project will be done in conjunction with the timing of our solar projects that are still in the planning stage.”
“Similarly for Townsville. And we do have customer demand for up to 1 GW of these projects in NSW. We’re looking at sites right now in NSW.”
Scaysbrook said the EnerQB solution offers a range of benefits not only to Quinbrook projects and customers but will also enhance grid stability and support the federal government’s Future Made in Australia initiative.
“Australia’s green superpower ambitions are entirely dependent upon how cheap we can make power in Australia,” he said. “That is the on-off switch for a Future Made in Australia.”
“Large-scale renewables, particularly solar teamed with battery storage is the engine room of the energy transition. It is the anchor technology combination to deliver low-cost power.”
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.