Australian-headquartered global mining company Fortescue Metals Group (FMG) has begun commissioning of a 100 MW solar farm at the North Star Junction, adjacent to its Iron Bridge ore mine, 140 kilometres south of Port Hedland, Western Australia (WA).
Fortescue Metals Chief Executive Officer, Dino Otranto said the commissioning began in the past quarter.
“During the past quarter we commenced commissioning of our 100 MW solar farm at North Star Junction, which will eliminate up to 180,000 tonnes of carbon dioxide equivalent from our operations every year once fully commissioned,” Otranto said.
The solar farm is part of the Pilbara Generation Project and compliments the Pilbara Transmission Project, which consists of 275 kilometres of high voltage transmission lines connecting Fortescue mine sites.
Also in the last quarter, the company began testing a hydrogen-powered battery electric haul truck prototype.
Fortescue Energy Chief Executive Officer Mark Hutchinson said the hydrogen-powered truck prototype also operated on hydrogen for the first time and will soon be transported to the Christmas Creek site to undergo site-based commissioning and testing.
Hutchinson added the company remains committed to green hydrogen.
“Our financial discipline will ensure that we focus hard only on those projects that are economic and deliver best value for shareholders,” Hutchinson said.
“We continue to progress our initial four green hydrogen projects across Australia, the United States, Norway and Brazil, which each draw on the unique strengths of the countries they are in.”
“Projects in Morocco, Oman, Egypt and Jordan will follow next, while we maintain a further pipeline of opportunities that will progress when power prices fall sufficiently to bring them to economic viability and global demand for green hydrogen increases,” he said.
Fortescue Zero green technologies also signed its first contracts to sell electrolysers from their Gladstone, Queensland facility and finalised a multi-year deal with Jaguar Land Rover in the United Kingdom to use Fortescue’s battery intelligence software, Elysia, in its next-generation electric vehicles.
The Gladstone electrolyser manufacturing facility will have the capacity to produce over 2 GW of proton exchange membrane (PEM) electrolyser stacks annually.
Fortescue is attempting to eliminate approximately 90% of its CO2 emissions associated with their iron ore operations by 2030, committing $6.2 billion (USD 4 billion) dollars to the plan, which will save 700 million litres of diesel, 15 million GJ of gas and avoid 3 million tonnes of CO2 equivalent emissions annually.
This content is protected by copyright and may not be reused. If you want to cooperate with us and would like to reuse some of our content, please contact: editors@pv-magazine.com.
By submitting this form you agree to pv magazine using your data for the purposes of publishing your comment.
Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.
You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.
Further information on data privacy can be found in our Data Protection Policy.